From the contractor’s BOQ to the certificate they sign.

PRJ-2601 — guest bedroom wardrobes and dressing room joinery for Al Tamayuz Fit-Out Contracting, on a 342,500.00 contract. Followed here from the estimate to the payment certificate, using the figures the system actually produces.

01 · QUOTATIONQT-2026-0090 · REV C

The estimate starts in their spreadsheet, not yours.

The main contractor sends a bill of quantities as a spreadsheet. ProLedger detects the header row and the serial, description, quantity and price columns, and lets you remap any of them before importing. Every save snapshots a version, so when the QS asks what changed between revision B and revision C, there is an answer.

  • Excel or CSV import, columns auto-detected and remappable per file
  • Version history you can list side by side
  • Submit for approval, then approve or reject — with who, and when
  • Converts straight to an invoice, or to an agreement that pulls the BOQ through
Quotation
QT-2026-0090 rev C
APPROVED
Guest bedroom wardrobes — laminate184,200.00
Dressing room joinery — veneered118,400.00
Ironmongery & accessories24,650.00
On-site installation15,250.00
Contract sum342,500.00
02 · CUTTING PLANCARP-WARDROBE-2400 · SEEDED TEMPLATE

The bill of materials is a cutting list.

Each line carries a quantity and its own waste percentage, because a back panel and a run of edge-banding do not waste alike. The optimiser nests panels onto 8×4 sheets with the blade kerf taken out — so the sheet count you buy against is the one the saw will actually produce.

Work-order costing then sets the estimate — BOM quantity times order quantity, plus planned labour — against materials actually issued and hours actually booked, and shows the variance. Scrap & yield records what was scrapped per work order, with the yield percentage and its cost.

This template is one of three seeded into a new company, alongside a 600mm base kitchen cabinet and a flush door.

Hinged wardrobe 2400 × 2400 — as seeded, before you price it
MaterialPartQtyWaste
MAT-PLY18Carcass panels (sides/shelves)4.000012%
MAT-MDF06Back panel1.00008%
MAT-LAMDoor + exterior laminate3.000010%
MAT-EDGEEdge-banding40.000010%
MAT-HINGEDoor hinges8.0000
MAT-HANDLEHandles6.0000
SRV-FABWorkshop fabrication16.0000
SRV-INSTOn-site installation6.0000
03 · DELIVERY, FLOOR BY FLOORDN-5188 · SIGNED ON SITE

A fit-out is delivered in pieces, so it is signed for in pieces.

Deliveries are raised against a quotation or sales order, signed off by the customer, and claimed as partial deliveries by component stage — frame, leaf, architrave, fixing, ironmongery, touch-up. The delivery register is what the claim is built from, so nobody reconstructs a month’s work from photographs in a WhatsApp group.

Delivery noteScopeStatusValue
DN-5119Levels 2-4Signed62,110.00
DN-5188Levels 2-5Signed112,570.00
DN-5196Levels 2-6Signed94,680.00
DN-5204Level 5On site73,140.00
04 · WORK IN PROGRESSIFRS-15 · PERCENTAGE OF COMPLETION

Work done and not yet claimed is the most expensive number in the business.

Revenue is recognised on percentage of completion and set against what has actually been billed. Over-billed is cash you hold against work you still owe; under-billed is work you have already paid your people to do and have not asked for. A spreadsheet shows neither.

ProjectScopeContract% completeOver / under billed
PRJ-2601Guest bedroom wardrobes342,500.0078.4%14,220.00
PRJ-2603Boardroom table & panelling196,400.0041.2%-8,940.00
PRJ-2605Reception counter, solid surface88,750.0096.0%3,110.00
START14 DAYS · YOUR OWN CONTRACT

Run your own contract through it.

Import a real bill of quantities, price a claim with the retention held back, and see whether the VAT ties out. The cutting-list templates above are waiting in the workspace on the day you sign up.